Resistive Reactive Load bank deployed in the City of London

Resistive Reactive Load bank deployed in the City of London

Loadgen were called on to deploy a 2.5Mva Resistive Reactive Load bank as part of an 8MW load test in the City of London.

This project required a quick turn-around, and involved substantial organisation with the logistical challenges posed by London City. Rising to the challenge, Loadgen supplied, installed, commissioned and de-commissioned the complete project over a seven day period.

To give an idea of the project's scale and time frame, with over four kilometers of cable to install, our service team worked across the weekend to ensure the turnkey project was ready for testing on the Monday morning.

07 Mar 2018